Accelerating the progress to complete Route 14 project

Route 14 project from Nguyen Tat Thanh street to Doc Lap street, Tuy Hoa city, commenced construction in 2020, but it has not been completed yet due to site clearance issues. Recently, Tuy Hoa city has completed site clearance, creating conditions for construction units to speed up the progress, determined to complete the project in September 2025.

Construction units focusing on machinery, equipment and human resources to complete the Route 14 project in September 2025
Construction units focusing on machinery, equipment and human resources to complete the Route 14 project in September 2025

The Route 14 project is invested by the provincial Management Board of Construction Investment Project, with a total investment of 238,48 billion dongs. The route is nearly 2,1km long, starting at Nguyen Tat Thanh street and ending at Doc Lap street. It has the width of 40m; of which the road surface is 15m wide, the median strip is 11m wide and the sidewalk is 14m wide. The route has been invested to complete asphalt concrete pavement, drainage system, trees, sidewalks, lighting and traffic safety system. Additionally, the project also includes the construction of a new railway bridge and a flood prevention pumping station for the railway underpass area.

The project aims to gradually complete infrastructure, develop socio-economy and partly concretize Resolution numbered 06 of the provincial Party Standing Committee on leading the construction and development of Tuy Hoa city towards green and sustainable growth; simultaneously, meeting the needs of urban development and exploiting land funds in the North of Tuy Hoa city; gradually forming and embellishing the architecture and urban landscape of the province.

According to the Management Board, the Route 14 project has been implemented since 2020; by the end of 2023, the section from Doc Lap street to the iron bridge is almost completed. However, about 500m from the railway bridge to Nguyen Tat Thanh street, the site clearance has not been completed yet because the people do not agree with the compensation, support and resettlement plan, causing the construction project to be unfinished and prolonged over the past time.

With the great determination and perseverance in propaganda as well as mobilization work, in early February 2025, Tuy Hoa city completed the site clearance. This has created favorable conditions for both the investor and contractors to speed up the construction progress of the project.

Immediately after completing the site clearance, the investor requested the contractors to concentrate machinery and equipment to speed up construction progress at these locations in order to soon complete the project on schedule.

Mr. Dam Thanh Phong, Head of Quality Management 3 Division of the Management Board, lets known: Currently, the site clearance issue has been resolved, the weather is also very favorable to speed up the progress of the Route 14 project. According to the registered plan, the units will complete the longitudinal sewer system, technical trenches, retaining walls and water collection tanks in the railway underpass area in the 2nd quarter; installing pumping station equipment, operating house and test operation in July; completing the construction of road surface, sidewalks, trees and lighting in August to be ready for operation and put into use in September this year. During this time, the Management Board will continuously monitor and supervise the project every day, every hour; ensuring the project to be completed with quality and progress according to the plan.

Translated by KHUONG THAO